All other trademarks and trade names mentioned in this document are the property of their respective holders. Notice The purchased products, services and features are stipulated by the contract made between Huawei and the customer. All or part of the products, services and features described in this document may not be within the purchase scope or the usage scope.
Page 3
About This Document Purpose This document describes the installation of the cabinet, boards, modules, and cables for the DBS3900 (Ver.B) (referred to as the DBS3900 in this document) deployed indoors or outdoors. It also provides checklists for hardware installation. Product Versions The following table lists the product versions related to this document.
Page 4
AC or DC power supply, the BBU can be installed in an APM30H, TMC11H, or OMB. When a DBS3900 is deployed indoors with DC power supply, the BBU can be installed in an IMB03, 19-inch rack of customers, or wall.
Page 5
14 Indoor Scenario with DC Power Supply (BBU Installed Indoors and RRU Powered Outdoors) In this scenario, a DBS3900 is deployed indoors with DC power supply. The installation of the BBU is not described in this scenario. An APM30H is installed outdoors, supplying power to and monitoring only RRUs.
DBS3900 (Ver.B) Installation Guide Contents Contents About This Document........................ii 1 Changes in the DBS3900 (Ver.B) Installation Guide..............1 2 Installation Preparations......................5 2.1 Document Preparation............................6 2.2 Tools and Instruments............................6 2.3 Skills and Requirements for Onsite Personnel....................7 3 Installation Scenarios........................8 4 Unpacking the Equipment......................22 5 Obtaining the ESN........................24...
1 Changes in the DBS3900 (Ver.B) Installation Guide Changes in the DBS3900 (Ver.B) Installation Guide This chapter describes the changes in the DBS3900 (Ver.B) Installation Guide. 06 (2011-09-15) This is the sixth official release. Compared with 05 (2011-08-30), this issue incorporates the following changes:...
Page 15
DBS3900 (Ver.B) Installation Guide 1 Changes in the DBS3900 (Ver.B) Installation Guide Compared with 04 (2011-07-15), no content is added. Compared with 04 (2011-07-15), no content is deleted. 04 (2011-07-15) This is the fourth official release. Compared with 03 (2011-06-10), this issue incorporates the following changes:...
Page 16
The procedures for installing cabinets, boards or modules, and related cables in an outdoor APM30H (Ver.B) or outdoor TMC11H (Ver.B). Compared with the DBS3900 Installation Guide of MBTS V100R003C00, WCDMA-NodeB V200R012C00, and GSM-BTS V100R012C00, this document omits the following topics:...
Page 17
DBS3900 (Ver.B) Installation Guide 1 Changes in the DBS3900 (Ver.B) Installation Guide The procedures for installing cabinets, boards or modules, and related cables in a scenario where the BBU is installed in an APM30, in an APM30H (Ver.A), TMC11H, or TMC11H (Ver.A).
This chapter describes document preparations, tool and instrument preparations, and skills and qualifications that installation engineers must possess. 2.1 Document Preparation Before installing a DBS3900, obtain related information in the following documents: 2.2 Tools and Instruments You must prepare the following tools and instruments before installation.
DBS3900 (Ver.B) Installation Guide 2 Installation Preparations 2.1 Document Preparation Before installing a DBS3900, obtain related information in the following documents: BBU3900 Hardware Description BBU3900 Hardware Maintenance Guide OCB User Guide For details about the installation of an RRU, see the following documents:...
Before the installation, pay attention to the following items: The customer's technical engineers must be trained by Huawei and be familiar with the proper installation and operation methods. The number of onsite personnel depends on the engineering schedule and installation environment.
AC or DC power supply, the BBU can be installed in an APM30H, TMC11H, or OMB. When a DBS3900 is deployed indoors with DC power supply, the BBU can be installed in an IMB03, 19-inch rack of customers, or wall.
The total number does not tally with the Find out the cause and report any missing packing list articles to the local Huawei office. Step 2 Check the exterior of the packing case. If ... Then ... The outer packing is intact...
APM30H. 6.1 Installation Process When a DBS3900 is deployed outdoors with AC power supply, and the BBU is installed in an APM30H, you must install the APM30H, components in it, and related cables. In addition, some optional components may be required based on actual requirements.
Page 40
Check the installation items, installation environment, and cable-related items after the cabinets and devices are all installed. 6.8 Power-On Check Before a DBS3900 starts operating, you must check the power-on status of the cabinet and components in it. 6.9 Subsequent Operations You must perform subsequent operations after installing a base station and checking related hardware installation.
APM30H) 6.1 Installation Process When a DBS3900 is deployed outdoors with AC power supply, and the BBU is installed in an APM30H, you must install the APM30H, components in it, and related cables. In addition, some optional components may be required based on actual requirements.
This section describes the procedures and precautions to be taken for installing power cables, transmission cables, monitoring signal cables, and CPRI cables when a DBS3900 is deployed outdoors with AC power supply and the BBU is installed in an APM30H.
----End 6.5.3 Installing Power Cables When a DBS3900 is deployed outdoors with AC power supply, the BBU can be installed in an APM30H. If a single APM30H is installed, the input power cable for the APM30H, BBU power cable, and RRU power cables must be installed. If multiple cabinets are installed in stack mode, the power cable between the APM30H and the TMC11H and that between the APM30H and the IBBS200D or IBBS200T must also be installed.
Step 5 Label the installed cables by referring to Attaching a Sign Plate Label. ----End 6.5.4 Installing Transmission Cables When a DBS3900 is deployed outdoors, transmission cables such as an E1/T1 cable, E1/T1 surge protection cable, FE/GE surge protection cable, FE/GE cable, or FE/GE optical cable must be installed based on onsite requirements.
----End 6.5.5 Installing Monitoring Signal Cables When a DBS3900 is deployed outdoors with AC power supply, the BBU can be installed in an APM30H. In this case, monitoring signal cables must be installed based on actual cabinet configurations onsite, which are one APM30H, one APM30H+one IBBS200D/IBBS200T, one...
Page 115
Installing Monitoring Signal Cables in a Scenario of one APM30H+one IBBS200D/ IBBS200T If a DBS3900 is configured with one APM30H and one IBBS200D or IBBS200T, two monitoring signal cables are required between the CMUA and the BBU in the APM30H and between the APM30H and the IBBS200D or IBBS200T.
Page 121
Installing Monitoring Signal Cables in a Scenario of one APM30H+two IBBS200Ds/IBBS200Ts If a DBS3900 is configured with one APM30H and two IBBS200Ds or IBBS200Ts, monitoring signal cables between the CMUA and the BBU in an APM30H, between the APM30H and the...
Page 127
Installing Monitoring Signal Cables in a Scenario of one APM30H+one TMC11H If a DBS3900 is configured with one APM30H and one TMC11H, monitoring signal cables between the CMUA and the BBU in the APM30H and between the BBU in the APM30H and the CMUA in the TMC11H must be installed.
Page 130
Installing Monitoring Signal Cables in a Scenario of one APM30H+one IBBS200D/ IBBS200T+one TMC11H If a DBS3900 is configured with one APM30H, one TMC11H, and one IBBS200D or IBBS200T, monitoring signal cables between the CMUA and the BBU in the APM30H, between the APM30H and the IBBS200D or IBBS200T, and between the APM30H and the TMC11H must be installed.
Page 136
Installing Monitoring Signal Cables in a Scenario of one APM30H+two IBBS200Ds/IBBS200Ts+one TMC If a DBS3900 is configured with one APM30H, one TMC, and two IBBS200Ds or IBBS200Ts, monitoring signal cables between the CMUA and the BBU in the APM30H, between the...
CAUTION The DBS3900 must be powered on within seven days after it is unpacked, and the period for which the DBS3900 remains powered-off during maintenance must not exceed 48 hours. Power-On Check in the Outdoor Scenario with AC Power Supply (BBU Installed...
TMC11H. 7.1 Installation Process When a DBS3900 is deployed outdoors with AC power supply and the BBU is installed in a TMC11H, you must install the TMC11H, components in it, and related cables. In addition, some optional components may be required based on actual requirements.
Page 161
7 Outdoor Scenario with DC Power Supply (BBU Installed Installation Guide in a TMC11H) Before a DBS3900 starts operating, you must check the power-on status of the cabinet and components in it. 7.8 Subsequent Operations You must perform subsequent operations after installing a base station and checking related hardware installation.
TMC11H) 7.1 Installation Process When a DBS3900 is deployed outdoors with AC power supply and the BBU is installed in a TMC11H, you must install the TMC11H, components in it, and related cables. In addition, some optional components may be required based on actual requirements.
This section describes the procedures and precautions to be taken for installing power cables, transmission cables, monitoring signal cables, and CPRI cables when a DBS3900 is deployed outdoors with DC power supply and the BBU is installed in a TMC11H.
----End 7.5.3 Installing Power Cables When a DBS3900 is deployed outdoors with DC power supply and the BBU is installed in a TMC11H, power cables such as an input power cable for the TMC11H, BBU power cable, and RRU power cables must be installed.
----End 7.5.4 Installing Transmission Cables When a DBS3900 is deployed outdoors, transmission cables such as an E1/T1 cable, E1/T1 surge protection cable, FE/GE surge protection cable, FE/GE cable, or FE/GE optical cable must be installed based on onsite requirements.
----End 7.5.5 Installing Monitoring Signal Cables When a DBS3900 is configured with one TMC11H, a monitoring signal cable between the CMUA and the BBU must be installed in the TMC11H. If another TMC11H is configured, another monitoring signal cable is required.
CAUTION The DBS3900 must be powered on within seven days after it is unpacked, and the period for which the DBS3900 remains powered-off during maintenance must not exceed 48 hours. Power-On Check in the Outdoor Scenario with DC Power Supply (BBU Installed...
+24 V DC APM30H. 8.1 Installation Process When a DBS3900 is deployed outdoors with AC power supply and the BBU is installed in a +24 V DC APM30H, you must install the APM30H, components in it, and related cables on site.
Page 233
8 Outdoor Scenario with DC Power Supply (BBU Installed Installation Guide in a +24 V DC APM30H) Before a DBS3900 starts operating, you must check the power-on status of the cabinet and components in it. 8.8 Subsequent Operations You must perform subsequent operations after installing a base station and checking related hardware installation.
+24 V DC APM30H) 8.1 Installation Process When a DBS3900 is deployed outdoors with AC power supply and the BBU is installed in a +24 V DC APM30H, you must install the APM30H, components in it, and related cables on site.
This section describes the procedures and precautions to be taken for installing power cables, transmission cables, monitoring signal cables, and CPRI cables when a DBS3900 is deployed outdoors with DC power supply and the BBU is installed in a +24 V DC APM30H.
----End 8.5.3 Installing Power Cables When a DBS3900 is deployed outdoors with DC power supply and the BBU is installed in a +24 V DC APM30H, power cables such as an input power cable for the APM30H, BBU power cable, and RRU power cables must be installed.
----End 8.5.4 Installing Transmission Cables When a DBS3900 is deployed outdoors, transmission cables such as an E1/T1 cable, E1/T1 surge protection cable, FE/GE surge protection cable, FE/GE cable, or FE/GE optical cable must be installed based on onsite requirements.
Figure 8-74 Coiling the optical fiber with winding plastic tape ----End 8.5.5 Installing Monitoring Signal Cables When a DBS3900 is configured with one +24 V DC APM30H, you must install a monitoring signal cable and in-position signal cable for the PSU (DC/DC). Procedure...
CAUTION The DBS3900 must be powered on within seven days after it is unpacked, and the period for which the DBS3900 remains powered-off during maintenance must not exceed 48 hours. Power-On Check in the Outdoor Scenario with DC Power Supply (BBU Installed...
(BBU Installed in an OMB) About This Chapter This chapter describes the procedures for installing an OMB, components in it, and related cables when a DBS3900 is deployed outdoors with DC power supply and the BBU is installed in the OMB. 9.1 Installation Process When a DBS3900 is deployed outdoors and the BBU is installed in an OMB, you must install the OMB, components in it, and related cables.
OMB) 9.1 Installation Process When a DBS3900 is deployed outdoors and the BBU is installed in an OMB, you must install the OMB, components in it, and related cables. In addition, some optional components may be required based on actual requirements.
9.3 Installing a BBU This section describes the procedure and precautions to be taken for installing a BBU in an OMB when a DBS3900 is deployed outdoors. Procedure Step 1 Install the mounting ears on both sides of the BBU reversely.
----End 9.4.4 Installing Power Cables When a DBS3900 is deployed outdoors with DC power supply and the BBU is installed in an OMB, power cables such as an input power cable for the OMB, BBU power cable, and RRU power cables must be installed.
Page 319
Step 5 Waterproof the connector. ----End Installing a BBU Power Cable A BBU power cable feeds power into the BBU from the DCDU-03B when a DBS3900 works in DC power supply scenario. Context Table 9-3 lists the specifications of a BBU power cable when a DCDU-03B supplies power.
----End 9.4.5 Installing Transmission Cables When a DBS3900 is deployed outdoors with DC power supply and the BBU is installed in an OMB, transmission cables such as an E1/T1 cable and E1/T1 surge protection transfer cable or FE/GE cable and FE/GE surge protection transfer cable must be installed based on actual requirements onsite.
Page 324
----End Installing an E1/T1 cable When a DBS3900 is deployed outdoors with DC power supply, the BBU can be installed in an OMB. In this case, an E1/T1 cable connects the surge protection unit and external transmission equipment for E1/T1 signal transmission.
Page 327
Step 3 Label the installed cables. For details, see Attaching an L-Shaped Label. ----End Installing a FE/GE Cable When a DBS3900 is deployed outdoors, a FE/GE cable connects the surge protection unit and external transmission equipment for FE/GE signal transmission. Procedure...
CAUTION The DBS3900 must be powered on within seven days after it is unpacked, and the period for which the DBS3900 remains powered-off during maintenance must not exceed 48 hours. Power-On Check in the AC Power Supply Scenario...
(BBU Installed in an OMB) About This Chapter This chapter describes the procedures for installing an OMB, components in it, and related cables when a DBS3900 is deployed outdoors with AC power supply and the BBU is installed in the OMB. 10.1 Installation Process When a DBS3900 is deployed outdoors and the BBU is installed in an OMB, you must install the OMB, components in it, and related cables.
OMB) 10.1 Installation Process When a DBS3900 is deployed outdoors and the BBU is installed in an OMB, you must install the OMB, components in it, and related cables. In addition, some optional components may be required based on actual requirements.
10.3 Installing a BBU This section describes the procedure and precautions to be taken for installing a BBU in an OMB when a DBS3900 is deployed outdoors. Procedure Step 1 Install the mounting ears on both sides of the BBU reversely.
----End 10.4.4 Installing Power Cables When a DBS3900 is deployed outdoors with AC power supply and the BBU is installed in an OMB, power cables such as an input power cable for the OMB, BBU power cable, and RRU power cables must be installed.
Page 359
Step 3 Label the installed cables. For details, see Attaching a Cable-Tying Label. ----End Installing a BBU Power Cable When AC power is fed into a DBS3900, a BBU power cable feeds power into the BBU from a power equipment (AC/DC). A BBU power cable feeds power into a BBU. Context...
----End 10.4.5 Installing Transmission Cables When a DBS3900 is deployed outdoors with AC power supply and the BBU is installed in an OMB, transmission cables such as an E1/T1 cable and E1/T1 surge protection transfer cable or FE/GE cable and FE/GE surge protection transfer cable must be installed based on actual requirements onsite.
Page 364
----End Installing an E1/T1 cable When a DBS3900 is deployed outdoors with DC power supply, the BBU can be installed in an OMB. In this case, an E1/T1 cable connects the surge protection unit and external transmission equipment for E1/T1 signal transmission.
Page 367
Step 3 Label the installed cables. For details, see Attaching an L-Shaped Label. ----End Installing a FE/GE Cable When a DBS3900 is deployed outdoors, a FE/GE cable connects the surge protection unit and external transmission equipment for FE/GE signal transmission. Procedure...
CAUTION The DBS3900 must be powered on within seven days after it is unpacked, and the period for which the DBS3900 remains powered-off during maintenance must not exceed 48 hours. Power-On Check in the AC Power Supply Scenario...
This section describes the procedures and precautions to be taken for installing PGND cables, power cables, transmission cables, monitoring signal cables or alarm cables, and CPRI cables in an indoor wall-mounted scenario for a DBS3900. 11.4.1 Cabling Requirements Cables must be routed according to the specified cabling requirements to prevent signal interference.
Vacant optical connectors must be covered with dustproof caps. 11.4.2 Installing PGND Cables When a DBS3900 is deployed in an indoor wall-mounted scenario, PGND cables such as a BBU PGND cable and DCDU-03B PGND cable must be installed. Installing a BBU PGND Cable A BBU PGND cable ensures proper grounding of a BBU.
Step 3 Label the installed cables. For details, see Labeling Power Cables. ----End 11.4.3 Installing Power Cables When a DBS3900 is deployed indoors with DC power supply, power cables such as a DCDU-03B power cable, BBU power cable, and RRU power cables must be installed. Installing a DCDU-03B Power Cable A DCDU-03B power cable feeds power into a DCDU-03B.
Step 4 Label the installed cables by referring to Attaching a Sign Plate Label. ----End 11.4.4 Installing Transmission Cables When a DBS3900 is deployed indoors with DC power supply, transmission cables such as E1/ T1 cables, FE/GE cables, and FE/GE optical cables must be installed based on onsite requirements.
Page 402
Installing a FE/GE Cable A FE/GE cable transmits baseband signals between a BBU and external transmission equipment when a DBS3900 is deployed indoors. Procedure Step 1 Connect one end of a FE/GE cable to the port labeled FE0 on the GTMU or WMPT in a BBU,...
CAUTION The DBS3900 must be powered on within seven days after it is unpacked, and the period for which the DBS3900 remains powered-off during maintenance must not exceed 48 hours. Power-On Check in the AC Power Supply Scenario...
This section describes the procedures and precautions to be taken for installing PGND cables, power cables, transmission cables, monitoring signal cables or alarm cables, and CPRI cables when a DBS3900 is deployed in a 19-inch rack. 12.4.1 Cabling Requirements Cables must be routed according to the specified cabling requirements to prevent signal interference.
Step 3 Label the installed cables. For details, see Labeling Power Cables. ----End 12.4.3 Installing Power Cables When a DBS3900 is deployed indoors with DC power supply, power cables such as a DCDU-03B power cable, BBU power cable, and RRU power cables must be installed. Installing a DCDU-03B Power Cable A DCDU-03B power cable feeds power into a DCDU-03B.
Step 4 Label the installed cables by referring to Attaching a Sign Plate Label. ----End 12.4.4 Installing Transmission Cables When a DBS3900 is deployed indoors with DC power supply, transmission cables such as E1/ T1 cables, FE/GE cables, and FE/GE optical cables must be installed based on onsite requirements.
Page 433
Installing a FE/GE Cable A FE/GE cable transmits baseband signals between a BBU and external transmission equipment when a DBS3900 is deployed indoors. Procedure Step 1 Connect one end of a FE/GE cable to the port labeled FE0 on the GTMU or WMPT in a BBU,...
CAUTION The DBS3900 must be powered on within seven days after it is unpacked, and the period for which the DBS3900 remains powered-off during maintenance must not exceed 48 hours. Power-On Check in the AC Power Supply Scenario...
About This Chapter This chapter describes the procedures for installing an IMB03, components in it, and related cables when a DBS3900 is deployed indoors and the BBU is installed in the IMB03. 13.1 Dimensions and Installation Clearance Requirements This section describes the dimensions and installation clearance requirements of the IMB03.
CAUTION The DBS3900 must be powered on within seven days after it is unpacked, and the period for which the DBS3900 remains powered-off during maintenance must not exceed 48 hours. Power-On Check in the AC Power Supply Scenario...
(BBU Installed Indoors and RRU Powered Outdoors) About This Chapter In this scenario, a DBS3900 is deployed indoors with DC power supply. The installation of the BBU is not described in this scenario. An APM30H is installed outdoors, supplying power to and monitoring only RRUs.
Page 514
14 Indoor Scenario with DC Power Supply (BBU Installed Installation Guide Indoors and RRU Powered Outdoors) Before a DBS3900 starts operating, you must check the power-on status of the cabinet and components in it. 14.8 Subsequent Operations You must perform subsequent operations after installing a base station and checking related hardware installation.
Indoors and RRU Powered Outdoors) 14.1 Installation Process When a DBS3900 is deployed indoors with DC power supply, the BBU is installed indoors, and RRUs obtain outdoor power supply, you must install a cabinet, components in it, and related cables.
----End 14.4 Installing Components When a DBS3900 is deployed outdoors with AC power supply, and the BBU is installed indoors, you must install the SLPU and USLP2s in an outdoor APM30H. 14.4.1 Installing a USLP2 A USLP2 is installed in an SLPU, providing surge protection for RRU monitoring signals.
This section describes the procedures and precautions to be taken for installing power cables and monitoring signal cables when a DBS3900 is deployed indoors with DC power supply, the BBU is installed indoors, and the RRUs obtain outdoor power supply.
CAUTION The DBS3900 must be powered on within seven days after it is unpacked, and the period for which the DBS3900 remains powered-off during maintenance must not exceed 48 hours. Power-On Check in the Indoor Scenario with DC Power Supply (BBU Installed...