SUN2000-100KTL-US User Manual Issue Date 2023-12-20 HUAWEI TECHNOLOGIES CO., LTD.
Page 2
Notice The purchased products, services and features are stipulated by the contract made between Huawei and the customer. All or part of the products, services and features described in this document may not be within the purchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information, and recommendations in this document are provided "AS IS"...
About This Document About This Document Purpose This document describes the Grid Support SUN2000-100KTL-USH0 (abbreviated as SUN2000) in terms of its installation, electrical connection, commissioning, maintenance, and troubleshooting. Before installing and operating the SUN2000, ensure that you are familiar with the features, functions, and safety precautions provided in this document.
Page 5
Supported Power Grid Earthing Systems. Added three power grid earthing systems supported by the SUN2000. Deleted the description that "The SUN2000 only supports the IT power grid mode" and that "The SUN2000 is mainly used for medium-voltage power grids. It delivers three-phase, three-wire output, which is then fed to a medium- voltage power grid through a step-up transformer."...
4.3 Determining the Installation Position..........................33 4.4 Installing the Mounting Bracket............................38 4.4.1 Support-mounted Installation............................39 4.4.2 Wall-mounted Installation............................. 40 4.5 Installing a SUN2000................................41 5 Electrical Connections......................45 5.1 Precautions....................................45 5.2 Selecting a Connection Mode............................46 5.3 Preparing Cables................................... 49 5.3.1 MBUS.....................................
Page 7
7.1.5.1.5 Setting Communications Parameters........................87 7.1.5.1.6 Setting the Support System............................ 89 7.1.5.1.7 Setting a File Save Path............................90 7.1.5.2 System Maintenance..............................90 7.1.5.2.1 Starting and Shutting Down the SUN2000....................... 90 7.1.5.2.2 Restoring Factory Settings............................91 7.1.5.2.3 Performing an AFCI Self-Test..........................91 7.1.5.2.4 Resetting the SUN2000............................91 7.1.5.2.5 Resetting Alarms.................................
Page 8
7.1.6.1.4 Setting Power Adjustment Parameters......................101 7.1.6.1.5 Setting User Parameters............................103 7.1.6.1.6 Setting a File Save Path............................104 7.1.6.2 System Maintenance..............................104 7.1.6.2.1 Starting and Shutting Down the SUN2000..................... 104 7.1.6.2.2 Restoring Factory Settings............................ 105 7.1.6.3 SUN2000 Upgrade...............................105 7.1.6.4 Device Logs..................................106 7.1.7 Querying the Status...............................
Page 13
1 Safety Information WARNING During the installation of PV strings and the SUN2000, the positive or negative terminals of PV strings may be short-circuited to ground if the power cables are not properly installed or routed. In this case, an AC or DC short circuit may occur and damage the SUN2000.
Page 24
SUN2000-100KTL-US User Manual 2 Overview Function The SUN2000 is a three-phase grid-tied PV string inverter that converts the DC power generated by PV strings into AC power and feeds the power to the power grid. Features Intelligent ● 6 independent maximum power point tracking (MPPT) circuits and 12 PV string inputs: Support the flexible configuration of 2+2+2+2+2+2 strings.
Figure 2-5 Supported power grid NO TE The SUN2000 supports the IT earthing system in PV-only scenario. The use of the SUN2000 in other types of earthing systems, such as TT, TN-C, and TN-C-S, is not recommended. (If such an earthing system is encountered, contact the Company's engineers.)
Page 30
PV strings, or the DC input voltage of each MPPT circuit is less than 600 V. Grid-tied indicator Steady green The SUN2000 is in grid-tied mode. The SUN2000 is not in grid- tied mode. Communication Blinking green The SUN2000 receives indicator communications data normally.
Page 31
Bluetooth module, or a USB data cable is inserted into the USB port of the solar inverter. For example, local maintenance includes data import and export using a USB flash drive, and connecting to the SUN2000 app over a WLAN module, a Bluetooth module, or a USB data cable.
Page 34
Note a: The fittings delivered with the SUN2000 contain the label of DC terminal operation warning. You are advised to attach the label at the bottom of the SUN2000 front side. Or you can select a position for attaching the label based on site requirements.
2.4 Working Principles 2.4.1 Conceptual Diagram The SUN2000 receives inputs from 12 PV strings. The inputs are grouped into 6 MPPT circuits inside the SUN2000 to track the maximum power point of the PV strings. The DC power is then converted into three-phase AC power through an inverter circuit.
Page 36
Operating In Operating mode: ● The SUN2000 converts DC power from PV strings into AC power and feeds the power to the power grid. ● The SUN2000 tracks the maximum power point to maximize the PV string output.
SUN2000-100KTL-US User Manual 3 Storage Storage The following requirements should be met when the SUN2000 needs to be stored prior to installation: ● Do not remove the packing materials, and check the packing materials regularly (recommended: every three months). If any rodent bites are found, replace the packing materials immediately.
The SUN2000 can be installed indoors or outdoors. ● Do not install the SUN2000 in a place where personnel are easy to come into contact with its enclosure and heat sinks, because the voltage is high and these parts are extremely hot during operation.
Page 42
Ensure that the installation surface is solid enough to bear the weight load. ● In residential areas, do not install the SUN2000 on dry wall or walls made of similar materials which have a weak sound insulation performance because the noises generated by the SUN2000 are noticeable.
Page 43
The SUN2000 can be support-mounted or wall-mounted. The installation angle requirements are as follows: ● Install the SUN2000 vertically or at a maximum back tilt of 15 degrees to facilitate heat dissipation. ● Do not install the SUN2000 at forward tilted, excessive back tilted, side tilted, horizontal, or upside down positions.
Page 44
Figure 4-5 Installation space requirements (back-to-back installation) NO TE For ease of installing the SUN2000 on the mounting bracket, connecting cables to the bottom of the SUN2000, and maintaining the SUN2000 in future, it is recommended that the bottom clearance be from 600 mm (23.62 in.) to 730 mm (28.74 in.). If you have any questions about the clearances, consult the local technical support engineers.
Figure 4-9 Position for binding the security torx wrench (1) Position for binding the security torx wrench The SUN2000 mounting bracket has four groups of tapped holes, each group containing four tapped holes. Mark any hole in each group based on site requirements and mark four holes in total.
● To prevent device damage and personal injury, keep balance when moving the SUN2000. ● It should take multiple persons or a pallet truck to move the SUN2000. ● Do not place the SUN2000 with its wiring terminals at the bottom contacting the floor or any other objects because the terminals are not designed to support the weight of the SUN2000.
Page 50
User Manual 4 Installation Procedure Step 1 Lift the SUN2000 from the packing case and move it to the installation position. Figure 4-13 Taking out a SUN2000 Step 2 Lift the SUN2000 and keep it upright. Figure 4-14 Lifting a SUN2000 and keeping it upright...
Page 51
When hoisting the SUN2000, keep balance to protect the SUN2000 from colliding with the wall or other objects. Figure 4-15 Hoisting a SUN2000 Step 4 Install the SUN2000 on the mounting bracket and align the SUN2000 enclosure with the mounting bracket. Figure 4-16 Mounting a SUN2000 Step 5 Secure the SUN2000.
5.2 Selecting a Connection Mode Cables of external devices can be connected to the SUN2000 maintenance compartment through a cable gland or through a pipe. Select a connection mode based on site requirements.
(industrial environment). ● If MBUS is selected, no RS485 communications cable is required to connect to the SUN2000, but the AC power cable needs to connect to a SmartLogger2000 that supports MBUS. For detailed operations, see SmartLogger2000 User Manual .
Page 59
● The SUN2000 supports the input from 12 PV strings. NO TICE The SUN2000 has an RCMU inside. Its external AC switch should be a three-phase circuit breaker or other AC load circuit breakers to safely disconnect the SUN2000 from the power grid.
Page 61
● The AC output power cable can be an aluminum alloy cable with a conductor cross-sectional area of 1 AWG to 3/0 AWG. ● The MC4 terminals delivered with the SUN2000 only support the 8 AWG DC input power cable. Using cables of other specifications may result in serious consequences.
● To ensure the system response speed, you are advised to connect less than 30 cascading SUN2000s on each COM port of the SmartLogger. ● The RS485 communication distance between the SUN2000 at the end and the SmartLogger cannot exceed 1000 m (3280.84 feet).
Page 63
● The SUN2000 supports the input from 12 PV strings. NO TICE The SUN2000 has an RCMU inside. Its external AC switch should be a three-phase circuit breaker or other AC load circuit breakers to safely disconnect the SUN2000 from the power grid.
Page 66
● The AC output power cable can be an aluminum alloy cable with a conductor cross-sectional area of 1–3/0 AWG. ● The MC4 terminals delivered with the SUN2000 only support the 8 AWG DC input power cable. Using cables of other specifications may result in serious consequences.
AC power cable, DC power cable, and communications cable, connect ground cables to the grounding point and PV side ground point. ● It is recommended that the SUN2000 ground cable be connected to a nearby ground point. Connect the grounding points of all SUN2000s in the same array to ensure equipotential connections to ground cables.
● Never open the host panel of the SUN2000. ● Before opening the maintenance compartment door, ensure that no electrical connections are made for the SUN2000 on the AC or DC side. ● If you need to open the maintenance compartment door in rainy or snowy days, take protective measures to prevent rain or snow entering the maintenance compartment.
Context ● A three-phase AC switch must be installed on the AC side of the SUN2000. To ensure that the SUN2000 can safely disconnect itself from the power grid when an exception occurs, select a proper overcurrent protection device in compliance with local power distribution regulations.
Page 70
● Ensure that AC terminations are secured. Failure to do so may cause the SUN2000 to malfunction or damage to its terminal block by issues such as overheating. ● Ensure that the jacket is in the maintenance compartment.
Page 71
NO TICE ● Ensure that AC terminations are secured. Failure to do so may cause the SUN2000 to malfunctioning or cause damage to its terminal block from issues such as overheating. ● The cable colors shown in the figures are for reference only. Select an appropriate cable according to the local standards.
SUN2000 are OFF. Failure to do so may result in electric shocks. ● When the SUN2000 is grid tied, it is not allowed to work on a DC circuit, such as connecting or disconnecting a PV string or a PV module in a PV string.
Page 73
● If an 8 AWG DC input power cable is selected, use the Staubli MC4 positive and negative metal terminals and DC connectors supplied with the SUN2000. ● If a 10 AWG DC input power cable is selected, use the recommended MC4 positive and negative metal terminals and DC connectors.
Commissioning 6.1 Checking Before Power-On Acceptance Criteria The SUN2000 is installed correctly and securely. DC switches and the downstream AC switch are OFF. All cables are connected correctly and securely. Used cable glands are sealed and locking caps are tightened.
Page 79
● Before turning on the AC switch between the SUN2000 and the power grid, use a multimeter set to the AC position to check that the AC voltage is within the specified range.
Connection Mode After the DC or AC side of the SUN2000 is powered on, you can connect the app to it through a WLAN module, a Bluetooth module or a USB data cable.
Page 81
The UI snapshots provided in this section correspond to the SUN2000APP 3.2.00.001 version. The figure is for reference only. NO TICE ● The configurable parameters of the SUN2000 vary with the device model and grid code. ● If you change the grid code, some parameters may be restored to factory defaults.
Page 82
The user accounts that can log in to the app are classified into common users, advanced users, and special users based on the responsibilities of PV plant operation personnel. ● Common user: Has the permissions of viewing SUN2000 data and setting user parameters. ● Advanced user: Has the permissions of viewing SUN2000 data, setting functional parameters, and maintaining devices.
● Huawei App Store (Android) ● Google Play (Android) After the app is installed, the SUN2000 symbol will be displayed as below: 7.1.3 Logging In to the App Prerequisites ● The DC or AC side of the SUN2000 has been energized.
Page 85
Step 2 Select a login user and enter the password. NO TICE ● The login password is the same as that for the SUN2000 connected to the app and is used only when the SUN2000 connects to the app. ● The initial passwords for Common User, Advanced User, and Special User are all 00000a.
7 Man-Machine Interactions NO TICE ● If you log in to the SUN2000 app after the device connects to the app for the first time or factory defaults are restored, the quick settings screen will be displayed. If you do not set SUN2000 basic parameters on the quick settings screen, the screen is still displayed when you log in to the app next time.
Power on or Power off, enter the login password, and tap OK. ----End 7.1.5 Operations Related to the Advanced User Ensure that the DC side of the SUN2000 is energized before setting grid parameters, protection parameters, and feature parameters. 7.1.5.1 Parameter Settings Ensure that the DC side of the SUN2000 is energized before setting grid parameters, protection parameters, and feature parameters.
Page 90
7 Man-Machine Interactions Table 7-4 Feature parameters Parameter Description Value Range MPPT multi-peak When the SUN2000 is used in scenarios ● Disable scanning where PV strings are obviously shaded, ● Enable enable this function. Then the SUN2000 will perform MPPT scanning at regular intervals to locate the maximum power.
Page 91
0 and the SUN2000 shuts down. The energy yield would be affected since it takes too long for the power to resume and SUN2000 to restart. The parameter does not need to be set for crystalline silicon and filmy PV modules.
Page 92
All PV strings connected. Communication The standards of certain countries and ● Disable interrupt regions require that the SUN2000 must ● Enable shutdown shut down after the communication is interrupted for a certain time. If Communication interrupt shutdown is...
Page 93
(min) for automatic shutdown for protection in case of communication interruption. Communication If this parameter is enabled, the SUN2000 ● Disable resumed startup automatically starts after communication ● Enable recovers. If this parameter is disabled, the SUN2000 needs to be started manually after communication recovers.
Disable to reduce power consumption. String monitor The SUN2000 monitors PV strings in real ● Disable time. If any PV string is abnormal (such as ● Enable the PV string is shaded or the energy yield...
● EUR ● GBP ● USD ● CNY ● JPY Electricity Set the SUN2000 revenue per kWh. [0, 999.999] price/kWh The revenue/kWh indicates the local electricity price, which is used to calculate the conversion revenue of the energy yield. ----End 7.1.5.1.5 Setting Communications Parameters...
Page 96
● 9600 same bus. ● 19200 RS485 protocol ● The SUN2000 can connect to the upper- ● Invalid protocol level management unit over MODBUS ● MODBUS RTU RTU, Sunspec, or AVM.
Item Description Value Range Box-type Set the number of the box-type [0, 511] transformer No. transformer connecting to the SUN2000. Winding No. Set the number of the winding connecting [0, 7] to the SUN2000. ----End 7.1.5.1.6 Setting the Support System Context Parameter settings of the support system may vary depending on the vendor.
Context In the Android system, you can modify the save path for user operation logs and SUN2000 logs and export logs from the path subsequently. Procedure Step 1 Choose Function Menu > Settings > File save path to set the file save path.
AFCI self-test and tap OK in the displayed dialog box to perform the test. ----End 7.1.5.2.4 Resetting the SUN2000 Context Reset the SUN2000, and it will automatically shut down and restart. Procedure Step 1 Choose Function Menu > Maintenance. The maintenance screen will be displayed. Step 2 Tap behind Reset, enter the app login password, and tap OK.
Context Smart I-V Curve Diagnosis can be used only after a license is purchased. The license file for Smart I-V Curve Diagnosis is stored in the SUN2000. The SUN2000 SN uniquely maps to the license. You can view the SUN2000 license information and obtain the license status through the license management.
Figure 7-17 License management ----End 7.1.5.2.8 Device inspection Context After a SUN2000 is put into use, it should be inspected periodically to detect any potential risks and problems. Procedure Step 1 Choose Function Menu > Maintenance > Inspection, and tap to start the SUN2000 inspection.
Step 1 Choose Function Menu > Device logs. The device log screen is displayed. Export and send logs by emails ----End 7.1.6 Operations Related to the Special User Ensure that the DC side of the SUN2000 is energized before setting grid parameters, protection parameters, feature parameters, and grid adjustment parameters. Issue 08 (2023-12-20)
SUN2000-100KTL-US User Manual 7 Man-Machine Interactions 7.1.6.1 Parameter Settings Ensure that the DC side of the SUN2000 is energized before setting grid parameters, protection parameters, feature parameters, and grid adjustment parameters. 7.1.6.1.1 Setting Grid Parameters Procedure Step 1 Choose Function Menu > Settings > Grid Parameters to set grid parameters.
SUN2000 must not export power to the power grid again when the grid voltage is below the value of Grid reconnection voltage lower limit after the SUN2000 shuts down due to a fault. Grid reconnection The standards of certain countries and...
Page 105
Phase angle offset The standards of certain countries and ● Enable protection regions require that the SUN2000 needs to ● Disable be protected when the three-phase angle offset of the power grid exceeds a certain value. 10 minute OV Specifies the 10-minute overvoltage [1 x Vn, 1.25 x Vn]...
● When HVRT is set to Enable and Level-1 OV protection is higher than HVRT triggering threshold, if the grid voltage is between HVRT triggering threshold and Level-1 OV protection, the SUN2000 could start and shut down repeatedly. Level-N UV Specifies the level-N undervoltage...
Page 107
Value Range (Vn: rated voltage) LVRT When the power grid voltage is abnormally ● Disable low for a short time, the SUN2000 cannot ● Enable disconnect from the power grid immediately and has to work for some time. This is called LVRT.
Page 108
For example, if you set HVRT reactive power compensation power factor to 2, the reactive current generated by the SUN2000 is 20% of the rated current when the AC voltage rises by 10% during HVRT. Grid voltage jump To meet the standards of certain countries...
Voltage rise The standards of certain countries and (100, 115] suppression active regions require that the SUN2000 must derating point (%) generate a certain amount of reactive power when the output voltage exceeds a certain value. ● This parameter is displayed when Voltage rise suppression is set to Enable.
Page 110
SUN2000 shuts down after receiving ● Enable the 0% power limit instruction. If this parameter is set to Disable, the SUN2000 does not shut down after receiving the 0% power limit instruction. Active power change Adjusts the change speed of the [0.1, 1000]...
The standards of certain countries and [Fn-5, Fn+5) over frequency regions require that the output active derating (Hz) power of the SUN2000 be derated when the grid frequency exceeds a certain value. Quit frequency of Specifies the frequency threshold for...
Context In the Android system, you can modify the save path for user operation logs and SUN2000 logs and export logs from the path subsequently. Procedure Step 1 Choose Function Menu > Settings > File save path to set the file save path.
Context Tap Device logs to export operation logs, as well as alarm records and energy yield information of the SUN2000 from the mobile phone. Procedure Step 1 Choose Function Menu > Device logs. The device log screen is displayed. Export...
Clear. Alarms that have been manually cleared can be viewed on the Historical Alarm screen. Figure 7-26 Alarm screen ----End 7.1.7.2 Querying SUN2000 Running Information Procedure Step 1 Choose Function Menu > Running Info. to query the running information. Issue 08 (2023-12-20)
Page 116
The Summary, Details, Support, and Insulation information tabs Resistance tab pages display relevant information about the SUN2000. Power flow ● Connection from PV strings to the SUN2000 diagram ● Connection from the SUN2000 to the power grid ● If the SUN2000 has generated an alarm, displayed on the screen.
7.1.8.1 Scanning SN Bar Codes Context The SUN2000 SN bar codes are obtained in centralized mode. These bar codes help set up mapping between SUN2000 names and SN bar codes on the SmartLogger and assist the SmartLogger to communicate with SUN2000s and commission SUN2000s.
Context The SUN2000 maintenance script is used to set SUN2000 commands. After the script file is copied to the USB flash drive, the SUN2000 executes the maintenance script to import or export configuration, export data, and upgrade devices. Issue 08 (2023-12-20)
7 Man-Machine Interactions 7.2.1 Exporting Configurations Procedure Step 1 Click Local maintenance script on the SUN2000 app to generate a boot script FusionSolar APP and SUN2000 APP User Manual . file, see the Step 2 Import the boot script file to a PC.
Verify that the ciphertext in the boot script file matches the login password of the SUN2000 app. If they do not match and you insert the USB flash drive for five consecutive times, the user account will be locked for 10 minutes.
Verify that the ciphertext in the boot script file matches the login password of the SUN2000 app. If they do not match and you insert the USB flash drive for five consecutive times, the user account will be locked for 10 minutes.
Step 2 Decompress the upgrade package. NO TICE ● When the login password of the SUN2000 app is the initial password, there is no need to perform Step 3–Step ● When the login password of the SUN2000 app is not the initial password, perform Step 3–Step...
Page 126
Verify that the ciphertext in the boot script file matches the login password of the SUN2000 app. If they do not match and you insert the USB flash drive for five consecutive times, the user account will be locked for 10 minutes.
● If two SUN2000s share the same AC switch on the AC side, power off the two SUN2000s. ● After the SUN2000 powers off, the remaining electricity and heat may still cause electric shocks and body burns. Therefore, put on protective gloves and begin servicing the SUN2000 15 minutes after the power-off.
8 Maintenance For details, see Man-Machine Interactions, or the SmartLogger or NMS user manual. Step 2 Turn off the AC switch between the SUN2000 and the power grid. Step 3 Set all DC switches to OFF. NO TE For the SUN2000-90KTL-H2 used in Australia, install the delivered screw for locking each DC switch.
Do not stand in front of the solar inverter during the restart. ----End 8.3 Routine Maintenance To ensure that the SUN2000 can operate properly for a long term, you are advised to perform routine maintenance on it as described in this chapter. CA UTION ●...
If the original packing materials are not available, put the SUN2000 inside a suitable cardboard box and seal it properly. 9.3 Disposing of the SUN2000 If the SUN2000 service life expires, dispose of it according to the local disposal rules for electrical equipment waste. Issue 08 (2023-12-20)
SUN2000-100KTL-US User Manual A Contact Information Contact Information If you need to consult any technical problem, dial the Huawei technical assistance center (TAC) hotline. Please provide the following information to receive better service. ● Customer Name ● Contact Info ●...